Why you should know about the resource allocation view when leveling?
Share
The Resource Allocation view (view tab > more views > resource allocation view) is perhaps the best view to use when you have MS Project do the leveling for you. This combination view combines the resource usage view and the Leveling Gantt view. To understand and appreciate its value, have a look at the images below. The first shows an over allocation and in the second you will see the delay of each task as a consequence of the leveling action.